Florida Canyon Reports Q4 Gold Production of 12,864 Ounces
The company stated: "Florida Canyon produced 12,864 ounces of gold and sold 12,920 ounces of gold during the fourth quarter 2025. Production during the quarter was derived from gold placed on the Phase IIIa leach pad, together with residual recovery from Phases I and II. Quarterly production reflected a one-time, temporary reduction in solution flow rates resulting from a liner tear in a solution pond identified during the fourth quarter. The liner was fully repaired by mid-November with no solution releases and no environmental impact. Solution flow rates were restored to normal levels prior to year-end. Preventative measures, including an additional protective liner and improved access to the affected area for personnel and equipment, have been implemented for more effective response in the unlikely event this occurs again in the future. Importantly, gold ounces associated with the reduced solution flow during the quarter were deferred, not lost, and are expected to remain recoverable through continued leaching. Based on leach pad inventories and normalized solution flow, the Company expects the majority of ounces deferred during the fourth quarter-estimated at approximately 2,000 to 3,000 ounces-to be recovered through ongoing leaching throughout 2026."
Trade with 70% Backtested Accuracy
Analyst Views on ITRG
About ITRG
About the author

- Financing Agreement Reached: Integra Resources has entered into a bought-deal financing agreement with Canaccord Genuity and Stifel Nicolaus Canada, with underwriters agreeing to purchase 16.18 million common shares at $3.40 each, expected to generate approximately $55 million in gross proceeds.
- Over-Allotment Option Granted: Integra has granted underwriters an over-allotment option to purchase up to 1.94 million additional shares, representing 12% of the offering, providing the company with additional financing flexibility if needed.
- Clear Use of Proceeds: The net proceeds from this financing will be allocated to pre-production capital expenditures at the DeLamar Project, including early works, procurement, and land acquisition, aimed at accelerating project development and mitigating risks.
- Negative Market Reaction: Despite the successful financing, Integra Resources' shares fell by 5% in after-hours trading, indicating market concerns regarding the company's future performance, which may impact investor confidence.
- Financing Agreement Reached: Integra Resources Corp. has entered into an agreement with Canaccord Genuity and Stifel Nicolaus to issue 16.18 million common shares at $3.40 each, expecting gross proceeds of $55.01 million to fund pre-production capital expenditures at the DeLamar Project.
- Over-Allotment Option: The company has granted underwriters an over-allotment option to purchase an additional 12% of shares, potentially increasing capital inflow post-offering and enhancing financial flexibility for project execution.
- Expected Closing Date: The offering is anticipated to close around February 9, 2026, subject to customary closing conditions, including approvals from the TSX Venture Exchange and the SEC, ensuring compliance and transparency in the process.
- Investor Information Disclosure: The company has filed a preliminary prospectus supplement to provide detailed information to prospective investors, demonstrating a commitment to transparency and investor protection in the financing process.
- Production Meets Guidance: Florida Canyon Mine produced 70,927 ounces of gold in 2025, aligning with the production guidance of 70,000-75,000 ounces, demonstrating the company's operational stability and reliability in gold mining.
- Significant Capital Investment: The company completed approximately $60 million in capital investments at Florida Canyon, covering mining, infrastructure, and equipment upgrades, aimed at enhancing production capacity and future growth potential.
- Enhanced Mine Flexibility: Key infrastructure and equipment improvements position Florida Canyon for greater production consistency and flexibility in 2026, supporting long-term operational performance.
- Cash Flow Supports Strategy: Cash flow from Florida Canyon not only funded mine reinvestments but also advanced technical progress and risk mitigation at the DeLamar and Nevada North projects, validating the strategic rationale behind acquiring Florida Canyon.

- Project Milestone: Integra Resources Corp's DeLamar Heap Leach Project has been selected for the U.S. Federal FAST-41 Transparency Projects Program, marking a significant enhancement in transparency regarding environmental reviews and authorizations, thereby accelerating the project's advancement.
- Economic Viability Confirmed: The 2025 feasibility study indicates that the DeLamar project is expected to produce 1.1 million ounces of gold equivalent over a 10-year mine life, with an average annual production of 106,000 ounces and an all-in sustaining cost of $1,480 per ounce, showcasing strong economic return potential.
- Increased Internal Rate of Return: Under base case gold and silver prices, the DeLamar project achieves an after-tax net present value of $774 million and an internal rate of return of 46%, while recent price increases elevate the after-tax NPV to $1.7 billion and IRR to 89%, indicating a substantial enhancement in profitability.
- Commitment to Environmental Review: Integra is committed to advancing the project under a rigorous NEPA process, with an anticipated 15-month review period by the BLM, which not only aids in compliance but also strengthens stakeholder collaboration, ensuring the project's sustainable development.

- Enhanced Project Transparency: Integra Resources Corp's DeLamar Heap Leach Project has been selected for the U.S. Federal FAST-41 Transparency Projects Program, aimed at improving visibility and predictability in federal environmental reviews by establishing project-specific timetables, thereby enhancing the efficiency and transparency of project advancement.
- Optimized Coordination Mechanism: The project will be assigned a dedicated project advisor from the Permitting Council, responsible for monitoring progress and facilitating coordination among federal agencies, ensuring active engagement during the environmental review process to expedite approvals.
- Clear Decision Timeline: According to the Bureau of Land Management's timeline, the DeLamar Project is expected to publish a Record of Decision in Q3 2027, marking an efficient 15-month National Environmental Policy Act (NEPA) review process, indicating a promising development outlook for the project.
- Significant Economic Potential: The feasibility study for the DeLamar Project indicates an expected production of 1.1 million ounces of gold equivalent over a 10-year mine life, with an average annual output of 106,000 ounces, and at base case gold and silver prices, the project's after-tax net present value reaches $774 million with a 46% internal rate of return, showcasing strong economic return potential.

- Federal Permitting Schedule: The U.S. Bureau of Land Management (BLM) has established a federal permitting timeline for Integra's DeLamar Project, with a Notice of Intent expected in Q2 2026 and a 15-month NEPA review period concluding in Q3 2027, significantly enhancing project feasibility and certainty.
- Significant Economic Benefits: The feasibility study for the DeLamar Project indicates an expected production of 1.1 million ounces of gold equivalent over a 10-year mine life, with an average annual output of 106,000 ounces at an all-in sustaining cost of $1,480 per ounce, showcasing strong economic return potential.
- Thorough Environmental Review Preparation: Since acquiring the project in 2017, Integra has completed nearly a decade of environmental baseline data collection and engineering studies, ensuring the project is well-prepared for rigorous environmental review and compliance with stringent standards.
- Enhanced Community Engagement: The project has actively engaged with surrounding communities and Tribal Nations during its development, gathering feedback to refine project design and ensuring that environmental impact assessments address various stakeholder concerns, promoting sustainable development.





